Koboko Water Supply System Commissioned
President Yoweri Kaguta Museveni companied by top government dignitaries, ministry officials and National Water & Sewerage Corporation (NWSC) top management hit a home run as he commissioned the Koboko water supply system yesterday.
The Koboko project is part of the projects that are being implemented under water management development program funded by the government of Uganda with the support of the World Bank.
In terms of implementation, National Water and Sewerage Corporation handled Arua and Koboko was done by the directorate of water development because at that time Koboko was still under the ministry. With the handover of Koboko to National Water and Sewerage Corporation, the system will be expanded to enable more people to access to piped water. So far what has been done is the primary infrastructure and NWSC will embark on doing the tertiary infrastructure. The ultimate capacity of the plant is approximately 6 million liters of water per day to serve the population up to 2040 and the population is estimated to be about 100,000 people and at the moment Koboko has about 50,000 people and about 21 years it’s estimated to be at 100,000.
“The design capacity is enough to for that purpose however, the initial capacity that is installed is about 1.5 million liters per day and will have to be expanded and during the project the need for addressing issues to do with the water sauce were highly emphasized because it’s not at its best during the dry season hence the ministry drilling some boreholes and production wells that can generate 2.4 million liters per day and one of the is going to be developed by the ministry leaving the other two under the development of National Water and Sewerage corporation.” Stated Eng. Johnson Amayo.
The construction works of the treatment plant were undertake by Zhonghao Overseas Construction Engineering Company Limited from China at a cost of UGX 33,950,426,230 for the town of Koboko under the supervision consultant, SGI Studio Galli Ingegneria S.R.I.
The physical structures include: intake structure at R. Kochi, Water Treatment plant, 3 phase power line construction to the intake and water treatment plant, Transmission and Distribution pipe lines, Public toilets and Teremunga Reservoir.
After the commissioning of the new treatment plant, H.E the President of the Republic of Uganda, Yoweri Museveni appreciated and applauded NWSC and its management for its continuous efforts in improving the lives of Ugandans through the provision of clean safe water for all.
Also in attendance was State Minister for water, Hon. Ronald Kibule, Minister of Information Technology and Information, Hon Frank Tumwebaze, State Minister for Finance, Investment and privatization, Hon. Evelyn Anite, Woman MP of Rakai, Hon. Kyinyamatama Ssubi Julie. Koboko district local leadership, NWSC top management led by DMD-TS Eng. Johnson Amayo.
NWSC is committed to 100% coverage, infrastructure expansion, increased geographical coverage, water quality and customer delight.